Reposted by Tom Resing
Last month, Floodlight used a thermal drone to find DataOne's data center in Vineland, NJ, running at least 45 gas-powered generators without a state permit.
Now, New Jersey regulators have issued their largest-ever fine against a data center.
floodlightnews.org
New Jersey says DataOne’s 62 generators are illegal. It’s letting them run for 45 more days.
The state's $1 million fine comes less than a month after Floodlight’s visual investigation publicly exposed the Vineland site’s generator fleet for the first time